JOHOR BARU: Construction of the Rapid Transit System Link (RTS Link) connecting Johor and Singapore is progressing smoothly, with the project reaching about 65% overall completion, according to its operator.
The information was shared with the media during Transport Minister Anthony Loke’s visit to the Bukit Chagar station construction site on Monday (Nov 3).
He said the RTS Link has three key components – the rail depot, the Bukit Chagar station and the Immigration, Customs and Quarantine (ICQ) complex – each showing strong progress.
“The link’s depot has reached 91% completion, the Bukit Chagar station is at 73%, while the ICQ complex has achieved 76.8%,” he told reporters after a briefing on the project.
Loke, who also toured each level of the building, said the structural works for the station and ICQ building have been completed, with work now advancing to system installation and passenger facilities.