SINGAPORE – A new station will be built on the Jurong Region Line (JRL) between Tengah and Choa Chu Kang, and is slated to open in the mid-2030s, said Acting Minister for Transport Jeffrey Siow.
He also told the House that the opening of the JRL has been delayed by six months to the middle of 2028 due to construction delays and testing.
The first stage of the JRL – which comprises 10 stations that will connect Choa Chu Kang to Boon Lay and Tawas within Jalan Bahar – was slated to open in end-2027. It was previously delayed by a year due to the Covid-19 pandemic.
“We will do our best to complete the works as soon as possible,” said Mr Siow during the debate on his ministry’s budget on March 4.
The Transport Ministry is projected to spend $16.15 billion in financial year 2026, up 1.4 per cent from $15.93 billion in the 2025 financial year.
In the interim, two shuttle bus services will be introduced to connect residents from selected JRL stations to “key destinations” in the region until the line opens, he said in response to Mr Ang Wei Neng (West Coast-Jurong West GRC).
On the new JRL station in Tengah, Mr Siow said it will serve future residents of the Forest Hill district in Tengah and open in tandem with the completion of nearby housing developments. Work has started on the new station, located at Jalan Lam Sam. It will bring the total number of JRL stations to 25.
In a statement on March 4, the Land Transport Authority (LTA) said it had worked with its JRL contractors to boost manpower and deploy more equipment to speed up construction, but could not make up the lost time from earlier delays due to the pandemic.
LTA also cited the complexity of the project as a factor. The JRL – Singapore’s seventh MRT line – is being built entirely above ground in a densely populated area.
Sections of the line are built close to HDB blocks and over major roads and expressways, including the PIE. Construction of the rail viaduct over the PIE could be done only at night, with road closures in place, LTA noted.
Certain works also took longer than planned, LTA said, citing the construction of a viaduct over a 25m-wide canal. It said its contractors had to carry out more extensive ground preparation around the canal to ensure the stability of the viaduct and other structures.
Choa Chu Kang West station under construction on Feb 26.
ST PHOTO: JASEL POH
The JRL will open in three stages, with Stage 1 now set for mid-2028. LTA said it would provide updates on Stages 2 and 3 as work progresses. Stage 2, from Tengah to Pandan Reservoir, is currently slated to open in 2028. Stage 3, which will extend the JRL into Nanyang Technological University and towards Jurong Pier, is scheduled to open in 2029.
LTA said the interim shuttle bus services will begin in end-2027 to improve transport capacity and connectivity between areas due to be served by the line. More details will be announced later, it added.
In his speech, Mr Siow also gave updates on upcoming MRT projects.
Construction of the third phase of the Cross Island Line (CRL) is slated to start in 2027, he said.





