JB developer ordered to pay US$2.58 million to condo owners, including Singaporeans, over delays

JB developer ordered to pay US.58 million to condo owners, including Singaporeans, over delays


The lawsuit, involving 145 named plaintiffs, was filed in 2019.

In 2021, the purchasers initially secured a court ruling in their favour without a full trial.

However, R&F successfully appealed that decision, leading to a 10-day trial that concluded in 2024. The latest ruling was delivered on Sep 10, 2026.

Ng said the prolonged fight had been worthwhile because it allowed the owners to pursue their claims collectively.