North-South Corridor opening delayed to 2029 in Singapore

North-South Corridor opening delayed to 2029 in Singapore


SINGAPORE – The 21.5km highway linking the northern towns to the city will be delayed by two years due to unexpectedly difficult ground conditions that require more complex construction work.

The North-South Corridor (NSC) viaduct, which runs from Admiralty West to Lentor Avenue, will now open in stages from 2029, instead of 2027.

The tunnel section from Lentor Avenue to East Coast Parkway will open in phases from 2031 instead of 2029, the Land Transport Authority (LTA) said on Sept 17.

From 2028, roads, footpaths and nearby areas affected by construction works will open in stages, and noise barriers will start coming down.

Pedestrian overhead bridges affected by the construction of the tunnel section will go back up from 2029.

With more than 90 per cent of the foundation works for the 8.8km viaduct and the 12.3km tunnel completed, works along the viaduct will focus on installing above-ground structures like columns, crossheads and viaduct segments.

As for the tunnel, most of the work will carry on underground from 2027, and help ease disruption to surrounding roads, LTA said.

The decision to push back opening dates by two years stems from delays at critical stages of construction, which had a knock-on effect on later stages of construction, LTA added.

This is despite efforts to carry on with works safely and optimise construction methods, it said.

In a press briefing on Sept 8, LTA detailed some of the challenges it faced as the project entered its most complex engineering phase.

The southbound tunnel during a site visit to the Novena section of the North-South Corridor on Sept 15.

The southbound tunnel during a site visit to the Novena section of the North-South Corridor on Sept 15.

ST PHOTO: KEVIN LIM

These include the ground conditions in Gambas Avenue and Woodlands Avenue 8, where the viaduct is located. In some parts, the rock-level underground was found to be higher and harder than expected, and the foundation work took longer than planned.