SINGAPORE: The opening of the North-South Corridor has been delayed by two years due to unexpectedly challenging ground conditions, the Land Transport Authority (LTA) said on Thursday (Sep 17).

The viaduct section, from Admiralty Road West to Lentor Avenue, is now expected to open in phases from 2029, instead of 2027 as previously announced.

The tunnel section, from Lentor Avenue to East Coast Parkway (ECP), is now expected to open in phases from 2031, instead of 2029.

Commuters and motorists along the corridor can expect travel conditions to improve as major structural works are completed, LTA said. Roads, footpaths and other adjacent areas occupied by construction will be progressively reinstated for public use from 2028.